A 3,200-ton project with an
estimated 43,300 production man-hours. The components of this
project included 2,400 tons of steel for the seating area of the
center, 560 tons of steel roof trusses, and 240 tons of tube
steel for the curtainwall system. The Resch Center houses 10,000
seats and encompasses approximately 120,000 square feet. The
Structural Steel included large, unique roof trusses.
Miscellaneous metal is unique in that it incorporates a handrail
system of cables and a ceiling net system. Deck and joist were
furnished by Merrill Iron also. Fabrication and Erection
schedules were consistently ahead of schedule during project. |